Installation Overview

Installing a synthetic golf green from PGD CHICAGO is simple, all you need to do is follow the simple step-by-step procedures outlined below. Remember, greens larger than 500 square feet are best installed by a certified PGD CHICAGO Distributor. Simply fill out the contact us form to get your green installed for you.

Step By Step Installation Instructions

  1. Determine location and size.
  2. Clear area for sub-base.
  3. Distribute the sub-base material.
  4. Compact sub-base.
  5. Determine placement of sleeves/cups.
  6. Dig holes for sleeves/cups.
  7. Place sleeves.
  8. Ready turf for seams (if applicable).
  9. Lay turf over sub-base.
  10. Seam the turf (if applicable).
  11. Cut outer edge of turf to design.
  12. Cut the holes and install the cups.
  13. Secure outer edge of turf.
  14. Sand-fill (if applicable).
  15. Finishing the green.
  16. Sink a putt and have fun!